Two guys arrived at 7 am to hang the wallboard. They would have finished today if they hadn’t run short a few sheets. The office and bathroom are done (except taping the seams), but the shop still has some work to go.
Day: April 9, 2014
April 8
April 8
Geothermal was supposed to be working last week. . .so we didn’t reorder fuel oil…and ran out Friday night. It’s done now and seems to be working. We’ll see how it does.
April 7
Terry and Tom were back today to hang the interior doors and clean up some odds and ends. I went around and poked the wiring through the insulation so we would know where to put the holes in the liner panels. Wallboard for the office and woodshop was delivered today. Everything is now out of the lift bay to prepare for the ceiling and liner panels.
[nggallery id=51 slideshow=caption template=caption]
April 4
Today insulation started. This went pretty quickly and made a big difference in the look of the interior. The walls are now insulated, ready for wallboard and liner panels. After the ceilings are up they will come back to blow insulation above the ceilings.
We don’t want to discuss geothermal right now.
[nggallery id=50 slideshow=caption template=caption]