December 5

The inside of the building is really starting to take shape with the framing going up. We can get a feel for the interior spaces now. 

Office and wood shop walls and plumbing rough-ins come next. Then things will slow down when the building is turned over for the electrical work (my job).  After that: inspection, insulation and interior finishes.

[nggallery id=43 slideshow=caption template=caption]

Bonus today . .  sneak preview of work going on inside the house.

[nggallery id=44 slideshow=caption template=caption]

December 4

Today was a very busy day . . . Jonas and his crew finished the last section of siding above the office area roof . . . PPL staked out the revised pole guy wires . . . the garage doors arrived, were set up and ready for operation . . . PPL’s contractor installed the electrical service from the pole to the building . . . trim work on the office porch continues and interior framing for the office started.  Barry came by to get some earthwork done, but it was too crowded!  A quote for heating arrived. Soon we can start moving in and taking some of the pressure off of constricted space in the house and old garage.

[nggallery id=42 slideshow=caption template=caption]